Concrete Bags Calculator
A 10 by 10 foot slab at 4 inches thick needs 62 eighty-pound bags of concrete with the standard 10% waste allowance — 1 pallet plus 20 loose bags, weighing 4,960 lb. Enter your slab, post holes, or known volume below for the exact bag count in every size.
Bag yields are the QUIKRETE Concrete Mix 1101 figures: 0.60 cu ft per 80 lb bag, 0.45 per 60 lb, 0.375 per 50 lb fast-setting, 0.30 per 40 lb — so it takes 45 eighty-pound, 60 sixty-pound, or 90 forty-pound bags to make one cubic yard. A standard pallet holds 42 bags of 80 lb, 56 of 60 lb, or 80 of 40 lb. Check your bag label, since fast-setting and high-strength mixes can differ slightly.
Estimates only — not a quote. Past about 1 cubic yard a short-load ready-mix truck usually beats bags on price and on your back. Concrete is heavy — about 4,000 lb per cubic yard — so plan the haul, not just the arithmetic.
How the concrete bags calculator works
Volume is pure geometry. A slab is length x width x thickness in feet: 10 x 10 ft at 4 inches is 10 x 10 x (4 / 12) = 33.33 cubic feet, or 1.23 cubic yards. A post hole is a cylinder minus the post itself: a 10-inch hole 24 inches deep around a 4x4 post (3.5 inches actual) holds pi x 5^2 x 24 = 1,885 cubic inches of hole minus 294 cubic inches of post, about 0.92 cubic feet per hole.
Bags are volume plus waste, divided by the yield of one bag, always rounded up — you cannot buy 0.4 of a bag, and running short mid-pour is the classic expensive mistake. With the trade-standard 10% waste allowance, the 10x10 slab becomes 36.67 cubic feet: 36.67 / 0.60 = 61.1, so 62 eighty-pound bags; 82 sixty-pound; 98 fifty-pound fast-setting; 123 forty-pound. The yields come from the QUIKRETE Concrete Mix 1101 data sheet.
Pallets and weight are the haul plan. A standard pallet holds 42 eighty-pound bags (3,360 lb), so 62 bags is 1 full pallet plus 20 loose bags, and 4,960 lb total — check your vehicle and trailer rating before you load it. At 45 eighty-pound bags per cubic yard, anything past about 1 cubic yard is worth pricing as a short-load ready-mix truck: the truck usually wins on both price and your back.
Worked example, post holes: six 10-inch holes, 24 inches deep, around 4x4 posts. Each hole nets about 0.92 cubic feet after the post, so six holes are 5.52 cubic feet; with 10% waste that is 6.08 cubic feet, or 6.08 / 0.60 = 10.1, rounded up to 11 eighty-pound bags — about 1.7 bags per hole. In high-wind or frost zones, dig 30 inches deep and budget 2.5 to 3 bags per post instead.
Common mistakes: forgetting the waste allowance — skipping 10% alone turns the 62-bag slab order into 56 and leaves you short; forgetting to subtract the post from a post hole, which over-orders by about 15%; and mixing bag sizes in one pour without checking yields, because a 50 lb fast-setting bag yields 0.375 cubic feet, not half of an 80 lb bag.
bags = ceil(volume in cu ft x (1 + waste) / yield per bag) · yields: 80 lb = 0.60, 60 lb = 0.45, 50 lb = 0.375, 40 lb = 0.30 cu ft · 1 yd³ = 45 x 80 lb bags
Related tools
Price the whole pour with the Concrete Slab Cost Calculator, check the volume alone with the Concrete Cubic Yard Calculator, or count bags for a cast top with the Concrete Countertop Calculator.
Concrete bags calculator FAQ
How many bags of concrete do I need for a 10x10 slab?
At 4 inches thick with the standard 10% waste allowance: 33.33 cubic feet becomes 36.67, which is 62 eighty-pound bags, 82 sixty-pound bags, or 123 forty-pound bags. Without the waste allowance it would be 56 eighty-pound bags — and you would likely run short.
How many bags of concrete make a cubic yard?
45 bags at 80 lb, 60 at 60 lb, 72 at 50 lb fast-setting, or 90 at 40 lb. A cubic yard is 27 cubic feet, and an 80 lb bag yields 0.60 cubic feet, so 27 / 0.60 = 45. These counts include no waste allowance.
How many bags of concrete per post hole?
A standard 10-inch hole 24 inches deep around a 4x4 post needs about 1.7 eighty-pound bags with 10% extra — six such holes take 11 bags. A 30-inch deep hole in a high-wind or frost zone needs 2.5 to 3 bags per post.
How many bags of concrete are on a pallet?
A standard factory pallet holds 42 bags of 80 lb concrete (3,360 lb), 56 bags of 60 lb, or 80 bags of 40 lb. A 62-bag order of 80 lb mix is 1 full pallet plus 20 loose bags.
Should I use bags or ready-mix concrete?
Bags win up to about 1 cubic yard (45 eighty-pound bags). Past that, a short-load ready-mix truck is usually cheaper per yard and far less work — 62 bags weigh nearly 2.5 tons and have to be mixed one wheelbarrow at a time.
What does an 80 lb bag of concrete yield?
0.60 cubic feet once mixed with water, per the QUIKRETE Concrete Mix 1101 data sheet. A 60 lb bag yields 0.45, a 50 lb fast-setting bag 0.375, and a 40 lb bag 0.30 cubic feet. Check your bag label — fast-setting and high-strength mixes can differ slightly.
How much waste should I add to a concrete order?
10% is the trade standard for slabs and post holes, covering spillage, form bulge, and uneven subgrade. Add 15% for rough or hand-dug forms. The allowance does not cover measuring wrong — measure twice.