SwiftTools

Chain Link Fence Calculator

A 150-foot chain link fence, 4 feet tall, with one 4-foot gate needs 14 line posts, 4 terminal posts, 7 top-rail sections and 3 rolls of fabric — plus 22 bags of concrete. Enter your fence below for the full parts list.

Your fence
fabric length = total length − gates × gate width · sections = ceil(fabric length ÷ spacing) · line posts = sections − 1 · terminal posts = 2 ends + corners + 2 per gate · rail sticks = ceil(fabric length ÷ rail length) · fabric rolls = ceil(fabric length ÷ 50) · concrete = 1 bag per line post + 2 per terminal post

The rules are the calcbuilt set, stated on the page: line posts are the light 1-7/8 in posts every 10 ft at most, terminal posts are the heavier 2-3/8 in posts at every end, corner and both sides of every gate, top rail comes in 21 ft sticks that swage together, and fabric comes in 50 ft rolls. Concrete is 1 eighty-pound bag per line post and 2 per terminal post. Some takeoffs use 10 ft rail sticks and 2 bags per line post with 3 per terminal — pick the rail length in the field above and add a bag per post if your supplier works that way.

Materials only, no cost. This page counts the parts — posts, rail, fabric, concrete, ties and fittings — not the installed price. Price the whole job with the Chain Link Fence Cost Calculator. Estimates only: confirm quantities with your supplier and local code before ordering, and call 811 before you dig.

How the chain link fence calculator works

Start with the fabric length, not the fence length: subtract the gate openings first. On the default fence — 150 feet with one 4-foot gate — the fabric run is 146 feet. Sections are that length divided by the post spacing, rounded up: 146 / 10 = 14.6, so 15 sections. Line posts are sections minus one, because the terminal posts hold the ends: 15 - 1 = 14. Terminal posts are 2 ends plus every corner plus 2 per gate — 2 + 0 + 2 = 4 on the default — and the total is 18 posts. That is the calcbuilt rule set, and it reproduces their worked example exactly.

Top rail and fabric are sold in fixed lengths, so both round up. Top rail comes in 21-foot sticks that swage together: 146 / 21 = 6.95, so 7 sticks. Fabric comes in 50-foot rolls: 146 / 50 = 2.92, so 3 rolls. The mesh area is the fabric length times the height — 146 x 4 = 584 square feet — which is what you need if your supplier sells fabric by the square foot or the roll height differs. Some suppliers sell rail in 10-foot sticks instead: pick 10 feet in the rail field and the same fence takes 15 sticks.

Post length follows the hole, not just the fence height. The hole is about a third of the fence height plus 6 inches, with a 2-foot minimum — on a 4-foot fence that is 4/3 + 0.5 = 1.83 feet, so the 2-foot minimum governs and the posts are 6 feet long. On a 6-foot fence the hole is 2.5 feet and the posts are 8.5 feet. Line posts go in 6-inch holes about 24 inches deep and terminal and gate posts in 8-inch holes 24 to 30 inches deep, deeper in frost country — the hole depth is a local-code matter, and the calculator shows the rule it used so you can check it.

Concrete follows the posts: 1 eighty-pound bag per line post and 2 per terminal post, because the terminals take the pull of the stretched fabric and are set deeper. The default fence takes 14 + 2 x 4 = 22 bags. The fittings follow the same logic: tie wires every 12 inches up each post and every 24 inches along the rail — 72 on the posts and 73 on the rail for the default, 145 in all — plus one tension bar per terminal post and three brace bands per terminal, 4 bars and 12 bands. Gate frames, hinges and latches are not counted: they come with the gate.

Worked example at a smaller scale: a 100-foot fence, 4 feet tall, 10-foot spacing, one 4-foot gate. Fabric length is 96 feet, sections 10, line posts 9, terminal posts 4, top rail 96 / 21 = 4.57 so 5 sticks, fabric rolls 96 / 50 = 1.92 so 2 rolls — the onetripdiy cross-check, matching exactly. A fence around three sides of a yard works the same way, run by run: count each run separately, because each run has its own ends and corners, and add the runs together at the end.

Common mistakes: counting the gate openings as fabric, which orders a roll too many; spacing line posts wider than 10 feet, which lets the fabric sag between posts; setting terminal posts at line-post depth, which lets the fabric pull them over; and forgetting the fittings — ties, bars and bands are cheap but a fence without them cannot be finished. And call 811 before you dig: a post hole through a buried line is the most expensive mistake on this page.

fabric length = total length - gates x gate width · sections = ceil(fabric length / spacing) · line posts = sections - 1 · terminal posts = 2 ends + corners + 2 per gate · rail = ceil(fabric length / 21) · rolls = ceil(fabric length / 50) · concrete = 1 bag per line post + 2 per terminal post · hole = max(2 ft, height / 3 + 6 in)

Related tools

Price the whole installed job with the Chain Link Fence Cost Calculator. For a wood fence, count the pickets with the Fence Picket Calculator, space the posts with the Fence Post Spacing Calculator, and price the boards with the Wood Fence Material Calculator or the Privacy Fence Material Calculator.

Chain link fence calculator FAQ

How many posts do I need for a chain link fence?

Subtract the gates, divide by the post spacing and round up for sections, then subtract one for line posts — the terminals hold the ends. A 150 ft fence with one 4 ft gate at 10 ft spacing is 15 sections, 14 line posts and 4 terminal posts, 18 in all.

What is the difference between line posts and terminal posts?

Line posts are the light 1-7/8 in posts that only hold the mesh up, spaced at most 10 ft apart. Terminal posts are the heavier 2-3/8 in posts at every end, corner and both sides of every gate — they take the pull of the stretched fabric, so they are set deeper and get an extra bag of concrete each.

How far apart should chain link fence posts be?

Line posts at most 10 feet apart — 8 feet is common on taller or heavier fences. Wider spacing lets the fabric sag between posts and makes the fence look wavy.

How long should chain link fence posts be?

Fence height plus the hole depth: about a third of the height plus 6 inches, with a 2-foot minimum. A 4 ft fence takes 6 ft posts, a 6 ft fence takes 8.5 ft posts.

How much concrete does a chain link fence need?

One 80 lb bag per line post and two per terminal post, on this page's rule — 22 bags for the default 150 ft fence. Some takeoffs use 2 bags per line post and 3 per terminal, which is 44 bags on the same fence: check what your supplier recommends for your soil.

How much chain link fabric do I need?

The fence length minus the gate openings, divided by 50 ft and rounded up to whole rolls. A 150 ft fence with one 4 ft gate needs 146 ft of fabric, so 3 rolls. The mesh area is 146 x 4 = 584 sq ft.

Do I need a permit or a utility check before installing a fence?

Check local code for height limits and setbacks — many places cap front-yard fences at 4 ft and require a permit above 6 ft — and always call 811 before you dig so buried lines are marked.